Builder asking interest for delay in disbursement other side he has delayed in possession
Hello,
I have purchased flat in pimpri chinchwad, pune. As per builder, flat was ready to move. After disbursement
of loan they can immediately give possession.
09.09.2019-Date of agreement. (I didn't get original agreement on same day)
This agreement has clause as below : The allottee herein shall pay the aforesaid agreed consideration to the Promoter and owner
herein within a period of 15 days from the date of execution of present Agreement.
20.09.2019-Received email from builder to collect all original document such as Registered agreement with
registration receipt & index II, Sanction Plan, Builder NOC, Demand Letter Rs. xyz/- dated 16.09.19 (Due Date 30.09.19),
GST Letter, All original payment receipts.
21.09.2019-I collected all documents and started chasing bank for home loan procedure but though bank has delayed.
So,from 20.09.2019 if we count 15 days it becomes 5 October.
5.10.2019-Ideal day of disbursement.
It took more than 1 month for first disbursement from bank.
06.11.2019-Actual First disbursement.
bank kept 10% disbursement delayed because of incompelete document provided by builder (completion certificate was not provided by
builder) at start time, later on 6.11.2019 he send completion certificate via email we have that email copy.
After submitting completion certificate, bank did remaining disbursement.
14.11.2019-last disbursement.
07.11.2019-Ideal day of possession but
17.12.2019-Actual day of possession
possession delayed because of incomplete work done as below
1. Kitchen basin leakage.
2. Wash basin pipe leakage.
3. Common washroom Mixer tap was broken and leakage, shower leakage, white cement was not
there nearby toilet which caused wetness in wall.
4. Master washroom hand shower leakage.
5. No flush knob in both toilets at starting.
6. After installing flush knob, it was leakage.
7. Master bedroom Toilet seat was leakage while operating flush.
8. Hall window changing.
9. Kitchen window mosquito net was tattered.
10. Cleaning was not proper.
I have chased so many times with builder, i dropped email as well give me possesion at the earliest i am paying rent to live
in pune but though it took 1 month 11 days to resolve all above mentioned problems.
Finally, I received Key handover letter 17.12.2019 and keys of flat.
Conclusion:
5th October (Ideal disbursement day) to 6th November (Actual disbursement day)=1 month, 1 day.
7th November 2019 (Ideal possession day) to 17th December 2019 (Actual possession day)=1 month, 11 days.
Now, builder is asking 1 month interest else he will not give me possession letter and also I think he will not move the
electicity meter to my name till we pay interest.
But builder also have delayed possesion, due to which I am living on rent for whole december month.
I could have started living in my new home by 1 december itself.
Can you please advise, I should pay interest amount or can I take any action by law?
Asked 4 years ago in Property Law
Religion: Hindu